220 kV Transmission Line and Substation Expansion — Issyk-Kul

Issyk-Kul Region2026Completed

220 kV Transmission Line and Substation Expansion — Issyk-Kul

A 32 km 220 kV overhead line and substation expansion to evacuate the output of the solar power plant.

Unigreen Solar Power Plant (SPP), 300 MW

Toru-Aigyr, Issyk-Kul Region2026In progress

Unigreen Solar Power Plant (SPP), 300 MW

A 300 MW solar power plant on the northern shore of Issyk-Kul — one of the largest renewable energy facilities in Kyrgyzstan.

Osh Region2026In progress

Konduk Small HPP

Construction of a small hydropower plant in Osh Region.

Jalal-Abad Region2026In progress

Kambarata HPP-2, Design

Design works for the Kambarata-2 hydropower plant.

Bala-Saruu Small HPP, 25 MW

Talas Region2024Completed

Bala-Saruu Small HPP, 25 MW

A 25 MW small hydropower plant on the Kirov reservoir: powerhouse, 110 kV switchyard building and derivation pipe.

Construction of a Dormitory for 225 People

Talas Region2023Completed

Construction of a Dormitory for 225 People

A 225-bed dormitory with a full range of exterior and interior works and engineering networks.

Kurpsai HPP: Overhaul of Two 200 MW Hydro Units

Jalal-Abad Region2022Completed

Kurpsai HPP: Overhaul of Two 200 MW Hydro Units

Overhaul of hydro units No. 2 and No. 4, each with a capacity of 200 MW.

Rehabilitation of At-Bashy HPP, 4×10 MW

Naryn Region2022Completed

Rehabilitation of At-Bashy HPP, 4×10 MW

Electrical works, replacement of hydraulic engineering equipment and installation of electrical equipment.

Tash-Kumyr HPP: Overhaul of a 150 MW Hydro Unit

Jalal-Abad Region2021Completed

Tash-Kumyr HPP: Overhaul of a 150 MW Hydro Unit

Overhaul of hydro unit No. 2 with a capacity of 150 MW.

Terek-Sai Substation and 110 kV Line Construction

Jalal-Abad Region2021Completed

Terek-Sai Substation and 110 kV Line Construction

110/6 kV and 110/35 kV substations and a 110 kV overhead line for a gold processing plant.

Construction of a Tuberculosis Hospital

Bishkek2020Completed

Construction of a Tuberculosis Hospital

A 4,500 m² hospital building: structural frame, full range of exterior and interior works, engineering networks.

Novotel Bishkek City Center

Bishkek2019Completed

Novotel Bishkek City Center

An international-brand hotel in central Bishkek, 18,700 m² — from the building frame to engineering and emergency systems.

Osh Airport — AFL and BHS Systems

Osh2015–2018Completed

Osh Airport — AFL and BHS Systems

Airfield lighting for runways and baggage handling systems: Vanderlande, Rapiscan, Youyang.

Construction of 110/35 kV Substations “Bishkek”, “Sport”, “Orto-Say”

Bishkek2018Completed

Construction of 110/35 kV Substations “Bishkek”, “Sport”, “Orto-Say”

Construction of substation buildings and installation of 110/35/10 kV electrical equipment, relay protection and SCADA.

Central Reference Laboratory

Almaty, Kazakhstan2016Completed

Central Reference Laboratory

An 8,000 m² laboratory complex with BSL-2, BSL-3 and ABSL units.

US Embassy in Kyrgyzstan

Bishkek2015Completed

US Embassy in Kyrgyzstan

Structural works for the main building, site utilities and construction works on a 12,000 m² facility.